Cayucos Vets Hall Restoration

Original Cayucos Vets Hall



Project Scope

The Vets Hall has been determined to have historic significance at the local, state and national level, and therefore the project's design and construction shall meet the Secretary of the Interior's Standards for the Treatment of Historic Properties. The scope of the rehabilitation project includes:

  • Removal of non-historic additions and rehabilitation of the original Cass warehouse (Main Hall)
  • Salvaging original historic materials for re-application; adding new-to-match where needed
  • Providing a new foundation 2.5 feet higher than current to address sea level rise
  • Installation of new steel framing between wood trusses to provide structural stability
  • Construction of a new addition with Art Gallery, History Museum and Kitchen in style to match the original historic building
  • Renovating the BBQ patio and picnic area adjacent to the Hall
  • Providing new ADA compliant exterior decking and boardwalk with access to the beach and the pier

Construction Schedule

  • Notice to Proceed Issued: December 5, 2022
  • Contract Schedule Total # of Days: 436 calendar days
  • Completion Date: February 15, 2024
  • Days Added to Contract: 28 days
  • Revised Contract Completion Date: March 18, 2024
  • Contractor's Planned Completion Date: December 20, 2024

Ongoing Construction Work - October 2024

  • Install exterior decking
  • Install gutters, downspouts & splash blocks
  • Pour concrete beach access ramp

Upcoming Construction Work

  • Install deck guardrails and handrails
  • Install flatwork around BBQ pits
  • Install wood flooring

Project Contacts

For more information, please contact Margaret Mayfield, Project Manager III, via email or call (805) 781-1523

Construction Photos


September 2024: Installation of concrete paving at Ocean Front St.


September 2024: Installation of BBQ shade structure footings


August 2024: Installation of kitchen cabinets


August 2024: Whitewashing of exterior redwood siding


July 2024: Installation of awning at front of building


July 2024: Installation of folding door (facing beach)


Installation of redwood siding at gable end walls

June 2024:  Installation of redwood siding at gable end walls


Reinstallation of historic redwood siding

June 2024: Reinstallation of historic redwood siding


Installation of redwood siding and wood shake roofing

May 2024: Installation of redwood siding and wood shake roofing


Installation of gypsum wall board

April 2024: Installation of gypsum wall board


Forming of concrete walls and ramps

April 2024: Forming of concrete walls and ramps


Installation of batt insulation

March 2024: Installation of batt insulation


Forming of concrete ramps

March 2024: Forming of concrete ramps


February 2024: Installation of concrete stem walls, ramps, stairs

 

February 2024: Installation of wood windows

 

January 2024: Weatherproof exterior walls

 

January 2024: Sheathe roof structure

 

December 2023: Framing/sheathing of exterior walls

 

November 2023: Removal of historic siding (to be stored for reuse)

 

November 2023: Framing of the south wall

 

October 2023: Framing of walls at the new addition

 

October 2023: Interior wall framing in the warehouse

 

September 2023: Installation of steel trusses in the historic warehouse.

 

September 2023: Construction of the foundation for the new addition

 

August 2023: The historic warehouse is moved back onto the new foundation

 

August 2023:  Temporary bracing of the warehouse structure

 

July 2023: Installation of new floor sheathing

 

July 2023: Installation of new floor framing

 

July 2023: Installation of new steel floor beams

 

June 2023: Removal of existing asphalt shingle roofing

 

June 2023: Installation of new concrete foundation

 

May 2023: Drilling and installation of concrete caissons for new building foundation 

 

Image previewApril 2023: The existing warehouse foundation is demolished.

 

Image previewApril 2023: The historic warehouse is lifted and moved off of its existing foundation.

 

March 2023: Removal of non-historic additions complete.

 

February 2023: Removal of exterior stucco reveals original redwood siding.

 

The Cayucos Veteran's Memorial Hall Rehabilitation project kicked-off construction on December 2, 2022 with a public 'groundbreaking' event.

Funding Partners

Construction of this project has been made possible with grant funds awarded to the project by the California Natural Resources Agency and California State Parks through programs funded by Proposition 68, and by the State Coastal Conservancy. Additionally, the community of Cayucos has raised over $500,000 in contributions for the project through the Restore the Cayucos Vets Hall Committee.

California Natural Resources Agency
Cultural, Community and Natural Resources grant program: $4,437,000 award

The mission of the California Natural Resources Agency is to restore, protect and manage the state's natural, historical, and cultural resources for current and future generations using creative approaches and solutions based on science, collaboration and respect for all the communities and interests involved.

California Department of Parks & Recreation
Locally-Operated State Parks grant program: $705,250 award

The mission of the California Department of Parks and Recreation is to provide for the health, inspiration, and education of the people of California by helping to preserve the state's extraordinary biological diversity, protecting its most valued natural and cultural resources, and creating opportunities for high-quality outdoor recreation.

State Coastal Conservancy grant: $345,000 award

The Coastal Conservancy is a California state agency, established in 1976, to protect and improve natural lands and waterways, to help people get to and enjoy the outdoors, and to sustain local economies along California's coast. It acts with others to protect and restore, and increase public access to, California's coast, ocean, coastal watersheds, and the San Francisco Bay Area. Its vision is of a beautiful, restored, and accessible coast for current and future generations of Californians.

Perspective Renderings of the Completed Project