Probation Department Building

 

Description

This project will design and construct a new two-story, 34,000 sf building that will be tailored to meet operational needs, accommodate future departmental growth, provide state of the art technology and infrastructure and improve convenience and access for public clients. The intent is to build a user friendly, accessible, safe, secure, and healthy environment for the Probation staff and the public.

Location/Conceptual Design

The new building  will be sited on a portion of the twenty-one-acre County parcel located north of the Johnson Ave. and Bishop St. intersection in the City of San Luis Obispo.  The site is currently occupied by several existing Health Agency facilities which shall remain occupied during the construction. The new Probation Department building shall be located behind the existing facilities, on an undeveloped portion of the parcel and will take access from Bishop St.

Project Contacts

For questions or additional information, please contact Shelly Cone at scone@co.slo.ca.us


Project Timeline

Receive Site Grading Permit: May 2024

Begin Site Development: June 2024

Submit Building Plans for Permitting: April 2024

Receive Building Permit: October 2024

Complete Construction: January 2026 (estimated)


Construction Progress Update

Completed Work

• Storm drain line, perforated pipe, and fine line installation

• Slab curb formwork removal and clean up

• Survey for stairs footings at northwest side of building


Ongoing Work

• Lower driveway buildup and compaction

• Underground line installation in lower and upper parking lots for electric vehicle charging stations

• Formwork installation for final section of northeast building wall and adjacent retaining wall

• Moisture control installation of northeast wall with prefabricated drainage system

• Backfill of northeast wall


Upcoming Work

• Concrete placement for final section of northeast building wall and adjacent retaining wall

• Formwork, steel reinforcement and concrete placement for stair footings

• Main and lateral gas line installation and connection to meter

• Structural steel erection

• Steel stairs installation


Construction Progress Photos

First of 3 lifts of waterproofing system consisting of drainage textile adhered to waterproof sheets at northeast building wall.


Completion of first lift of waterproofing system and compaction of dirt prior to installation of second lift of waterproofing system.


Adhesive application for drainage textile of second lift of waterproofing system at northeast building wall.


Formwork layout and construction for final section of northeast building wall and adjacent retaining wall.


Project Updates

June 3, 2024

Construction work commences.


May 23,2024

Grading Permit received from County Building Department.


April 2, 2024

Building Plans submitted to County Building for permitting.


December 8, 2023

Site Plans were submitted to the Building Department for plan check review to receive a Grading Permit.


March 10, 2023

The official 'Notice to Proceed' was issued to F&H Construction to commence the work for the final design and construction of the Probation Department Building. 


January 24, 2023

The County Board of Supervisors approved the award of the Design-Build contract for the final design and construction of the New Probation Department Building to F&H Construction.


October 18, 2022

The County concluded the evaluation process for the Proposals received from the short-listed Design-Build Entities and issued the Notice of intent to Award the Design-Build contract to F&H Construction from Lodi, CA.


June 7, 2022

The County released the Request for Proposals to the three pre-qualified Design-Build Entities shortlisted through the County’s Request for Statement of Qualifications process, and who are interested in designing and constructing the County’s New Probation Department Building. The County will receive Proposals on September 15th, 2022 and will be Scoring and Qualifying firms to get to the top-ranked Proposal and Design-Build Team by mid-November.